Planning to upgrade your South Florida home with impact windows but uncertain about the time commitment? Understanding the realistic timeline for impact window installation helps you coordinate schedules, plan around family events, and set proper expectations. The installation process typically spans 2-6 weeks from initial consultation to final walkthrough, though several variables influence this timeframe significantly.
Breaking Down the Impact Window Installation Process

The professional impact window installation process involves multiple distinct phases, each requiring specific timeframes and coordination between homeowners, contractors, manufacturers, and local building departments.
Initial Consultation and Assessment (1-3 Days)
Your journey begins with a comprehensive home assessment. A Florida Certified General Contractor visits your property to measure existing openings, evaluate structural requirements, discuss design preferences, and review your specific hurricane protection needs. This phase typically requires 2-3 hours for most residential properties in Palm Beach or Broward County.
During this consultation, you’ll review product options from industry-leading manufacturers including PGT, CGI, ES Windows, and Hurricane Master. Each manufacturer offers distinct features, performance ratings, and aesthetic options that influence both pricing and lead times.
Proposal Development and Contract Signing (3-7 Days)
Following the initial assessment, your contractor prepares a detailed proposal outlining specifications, product selections, pricing, and estimated timelines. Review this document carefully, asking questions about Florida Building Code compliance, warranty coverage, and installation schedules.
Once you approve and sign the contract, the project officially enters the production phase. This milestone typically occurs within one week of the initial consultation, though complex projects requiring engineering calculations may need additional time.
Manufacturing and Production Lead Times
Manufacturing timelines represent the longest phase of the impact window installation process, varying significantly based on product selection, customization requirements, and current industry demand.
Standard Impact Windows (4-8 Weeks)
Stock-size impact windows from major manufacturers typically require 4-6 weeks for production. These windows meet Florida’s stringent hurricane protection requirements and undergo rigorous testing before leaving the factory. During peak season—typically May through October in South Florida—lead times may extend to 8 weeks as manufacturers handle increased demand.
Custom Impact Products (6-12 Weeks)
Custom-sized windows, specialty shapes, or premium finishes require extended manufacturing periods. Architectural homes in communities throughout Martin, Lee, or Charlotte County often feature unique opening sizes that necessitate fully custom fabrication. These products may require 8-12 weeks, particularly if they incorporate specialized glass options like low-E coatings or specific tinting.
Impact Doors and Garage Doors
Impact-rated entry doors from manufacturers like Therma-Tru and Lawson typically follow similar timelines to standard windows. However, custom impact glass garage doors from manufacturers including Amarr and Clopay may require 6-10 weeks due to the engineering complexity of these large-scale installations. These specialized garage doors provide hurricane protection while maintaining aesthetic appeal and functionality.
Permitting and Approval Timeframes
Florida’s strict building codes require proper permitting for impact window installations—a critical step that protects homeowners and ensures code compliance.
Permit Submission Process (1-3 Days)
Professional contractors handle permit applications on your behalf, submitting detailed plans, product specifications, and engineering documents to local building departments. In Palm Beach County, Broward County, and throughout Southwest Florida, this process requires precise documentation demonstrating code compliance.
Building Department Review (1-4 Weeks)
Municipal review periods vary significantly by jurisdiction. Some Collier County projects receive approval within one week, while complex installations in other jurisdictions may require three to four weeks. Experienced contractors familiar with local building departments navigate this process efficiently, addressing questions promptly to avoid delays.
Your contractor coordinates permit approval with manufacturing schedules, ensuring products arrive when installation approval is secured. This synchronization prevents storage issues and streamlines the overall impact window installation timeline.
Actual Installation Duration
Once products arrive and permits are approved, physical installation begins—the most visible phase of the project.
Single-Family Homes (2-5 Days)
Most residential impact window installations in South Florida complete within 2-5 days, depending on the number of openings and project complexity. A typical single-story, three-bedroom home with 15-20 windows usually requires 3-4 days of active installation work.
Professional installation teams work systematically, replacing several windows daily while maintaining your home’s security and weather protection. Installers remove existing windows, prepare openings, install new impact-rated units, seal and weatherproof perimeters, and clean work areas before departing each day.
Larger or Multi-Story Properties (1-2 Weeks)
Expansive homes, particularly those common in waterfront Palm Beach communities or gated Southwest Florida neighborhoods, may require 5-10 days for complete installation. Multi-story homes necessitate additional safety equipment, scaffolding, or lift rentals that extend timelines while ensuring installer safety and proper installation techniques.
Impact Door and Garage Door Installation
Impact-rated entry doors typically install in 4-6 hours per door, though custom configurations may require additional time. Custom impact glass garage doors demand more extensive installation efforts—usually 6-8 hours per door—due to their size, weight, and mechanical complexity. These specialized installations require experienced technicians familiar with both hurricane protection requirements and garage door operation systems.
Factors That Influence Your Installation Timeline
Several variables affect how long your complete project takes from initial consultation to final inspection.
Property-Specific Considerations
Structural modifications extend timelines when existing openings require reinforcement or resizing. Older homes throughout South Florida sometimes need header reinforcement, stucco repair, or concrete work before new impact windows install properly. These situations add 1-3 days to installation schedules.
Accessibility challenges—such as homes with limited street access, gated communities with restricted work hours, or properties requiring boat access—may also affect scheduling efficiency.
Weather and Seasonal Factors
Hurricane season creates competing demands. While many homeowners wisely schedule installations during spring or early summer, unexpected weather events can temporarily halt exterior work. Professional contractors monitor forecasts closely, protecting open installations and rescheduling when necessary to ensure proper installation quality.
Product Availability and Supply Chain
Industry-wide factors occasionally impact manufacturing lead times. High-demand periods following regional hurricane activity or supply chain disruptions affecting raw materials can extend production schedules. Working with established manufacturers like PGT, CGI, and ES Windows typically minimizes these concerns, as larger manufacturers maintain better inventory management and production capacity.
Post-Installation Inspections and Final Steps
The impact window installation process doesn’t conclude when installers finish their work.
Final Building Inspection (1-2 Weeks)
Local building departments conduct final inspections verifying installation quality and code compliance. Scheduling these inspections typically requires 1-2 weeks’ notice, though timeframes vary by jurisdiction and seasonal demand. Your contractor coordinates this inspection, addresses any inspector comments, and obtains final approval.
Project Closeout and Documentation
Upon passing final inspection, you receive essential documentation including building permits, inspection certificates, product warranties, and care instructions. Maintain these documents carefully—they’re valuable for insurance claims, future home sales, and warranty service.
Expediting Your Installation Timeline
While certain factors remain beyond control, homeowners can take proactive steps to minimize project duration.
Plan During Off-Peak Seasons
Scheduling consultations during fall or winter often yields faster manufacturing and installation timelines. Contractors and manufacturers experience lower demand during these months, potentially reducing wait times by 2-4 weeks compared to peak hurricane season scheduling.
Make Prompt Decisions
Quick decision-making regarding product selections, colors, and contract approvals keeps projects moving forward. Delayed responses add unnecessary time to already lengthy manufacturing periods.
Choose Experienced Local Contractors
Working with established Florida contractors experienced in local permitting processes, building codes, and manufacturer relationships streamlines every project phase. Their existing relationships with building departments and manufacturer representatives often facilitate faster approvals and priority production scheduling.
Realistic Expectations for South Florida Homeowners
Most complete impact window installation projects in Palm Beach, Broward, Martin, Lee, Charlotte, and Collier counties span 6-10 weeks from initial consultation to final inspection. Projects requiring extensive custom work, multiple impact doors, or custom impact glass garage doors may extend to 12-14 weeks.
This timeline includes consultation, manufacturing, permitting, installation, and final inspection. While seemingly lengthy, this process ensures proper engineering, code compliance, and installation quality that protects your family and property for decades.
Understanding this realistic timeline helps you plan accordingly, whether you’re preparing before hurricane season, coordinating with other home improvements, or scheduling around family commitments.
The Value of Professional Installation
Professional impact window installation delivers benefits extending far beyond hurricane protection. Energy efficiency improvements reduce cooling costs in South Florida’s climate, while noise reduction creates more peaceful indoor environments. Enhanced security protects your property year-round, and most homeowners qualify for insurance premium reductions—often 15-45% annually.
These benefits require proper installation by experienced professionals using quality products from trusted manufacturers. Rushing the process or cutting corners compromises performance and potentially endangers your family during severe weather events.
Ready to Begin Your Impact Window Project?
Understanding the impact window installation timeline empowers you to make informed decisions and plan effectively. While the process requires patience, the result—comprehensive hurricane protection, improved comfort, and enhanced property value—justifies the investment of time and resources.
Working with a military family-owned, Florida Certified General Contractor ensures your project receives professional attention at every phase. From initial consultation through final inspection, experienced contractors coordinate manufacturing, permitting, and installation while keeping you informed throughout the process.
Don’t wait until hurricane warnings prompt rushed decisions. Contact a trusted South Florida impact window specialist today to schedule your consultation and begin the process of protecting your home, family, and investment with professionally installed impact windows, doors, and custom impact glass garage doors.